November 18, 2018 Scheduled Power Interruption: Maragmag-Aglayan-Casisang 69kv line

BUSECO POWER ADVISORY!

To our valued MCOs:

Please be informed that NGCP will be implementing the following scheduled power interruption on our Maramag-Aglayan-Casisang 69 kV Line on Sunday, November 18, 2018 in order to facilitate the repair of 75 MVA Power Transformer (oil leak) at NGCP Maramag Substation:

1. From 8:00 to 8:30 AM – Load transfer of Maramag-Aglayan-Casisang 69 kV Line from NGCP Maramag Substation to NGCP Kibawe Substation

2. From 4:30 to 5:00 PM – Shifting back of Maramag-Aglayan-Casisang 69 kV Line from NGCP Kibawe Substation to NGCP Maramag Substation

Affected Areas:
City of Malaybalay, Municipalities of Lantapan and Cabanglasan, Eleven Brgys of Talakag, Bulonay of Impasug-ong and Lilingayon of Valencia City

This is for your information and reference.

Thank you for your extended patience and understanding.